NTMWD Plant Smart 2024

Davis growing in square footage, students

by | Jul 23, 2015 | Education

By Nancy Whitney

Staff Writer

[email protected]

Davis Intermediate will see some major renovations over the next two years. The improvements are due to the passing of the $94.2 million bond on Nov. 4, 2014, where $6.380 million of that will go to Davis.

“Many renovations have taken place this summer and will continue throughout this school year,” Davis Principal Barbara Rudolph said. “The passing of the bond lets the school district know that the community is behind them; that the community values education and that the community is proud to support educational opportunities that are being made available to the children in Wylie.”

Beginning in May, with an expected completion in September, Gallagher Construction began work on the 10-year-old school.

Projects are addressing renovations and additions, security and technology upgrades. New carpets and floor tiles will span the school, new bleachers will be installed in the gym, hand dryers will be installed in all bathrooms, the concrete outside the café and band hall will be replaced and the gym floors will be refinished and painted.

Safety concerns will be met by installing a badge system, access control and cameras. First responders will be able to access the cameras outside of the school. Entry lighting will be installed to provide better visibility.

Davis students will see updated technology throughout the facility when they return in September. There will be a new paging/bell system; digital menu boards; a new sound system for the cafeteria, band hall, choir room and gym; updated digital signage, the addition of wireless access points and upgrades to the network and network switching closets.

Clocks, which were not replaced in 2013, will be replaced at some point by 2017.

Executive Director of Communications and Community Relations, Ian Halperin, said the district is preparing for the overall growth across all grade levels by making some major additions and renovations to Davis Intermediate, including additional two story classrooms. The main entrance and classrooms will also be renovated for science and library use, including additional cafeteria space.

Rudolph said the faculty is excited that the school’s community will continue to grow.

“With growth comes additional opportunities and creative ways to educate, meet the needs of our students and strengthen the Wylie community,” Rudolph said. “The staff is committed to working as a collaborative team to do whatever it takes to help children succeed. Each year, we look forward to bringing our students together to build a strong community unified for excellence and committed to success.”

The exterior and interior of the school will get a fresh coat of paint beginning in May 2016 and new LED lighting will brighten up the parking lot.

Construction projects throughout the district are under the management of Gallagher Construction Services and PBK Architects.

For additional information on Davis Intermediate construction visit http://www.wylieisd.net/domain/2498.

 

 

NTMWD Plant Smart 2024

0 Comments

Related News

Sachse High School Principal wins award

Sachse High School Principal wins award

Creel named Region 10 Outstanding Principal of the Year SACHSE — Shae Creel, principal of Sachse High School, has been selected by the Texas Association of Secondary School Principals (TASSP) as the Region 10 Outstanding Principal of the Year. The honor recognizes...

read more
Trustee election for WISD cancelled

Trustee election for WISD cancelled

Howard, Reising, Kennon to fill seats The bi-annual trustee election originally scheduled for Nov. 5 for Wylie Independent School District was officially cancelled last week. Since each of the places up for election did not have two or more candidates, the district...

read more
Wylie ISD adopts tax rate for 2024-25

Wylie ISD adopts tax rate for 2024-25

With no meeting in July, Wylie ISD trustees took care of some required business and heard educational updates, including the current status of STAAR scores. Items on the Monday, Aug. 19, agenda included adopting a tax rate for maintenance and operations (M&O), as...

read more
B.I.G. Feed fights food insecurity in Wylie ISD

B.I.G. Feed fights food insecurity in Wylie ISD

Students from the Adulting Well class at Wylie High help pack more than 80 food bags each week for WISD students in need through the backpack/B.I.G. Feed program. Courtesy Rebekah Rodgers Driven by the urgent need to address students’ weekend hunger, the B.I.G. Feed...

read more
Lawsuit blocks TEA from releasing scores

Lawsuit blocks TEA from releasing scores

A hearing is scheduled Monday, Aug. 26, in Austin on a lawsuit temporarily blocking the Texas Education Agency (TEA) from releasing its A-F accountability ratings for public schools, a move that prolongs the ongoing legal battle over the state’s educational assessment...

read more
Trustee election filing deadline nearing

Trustee election filing deadline nearing

Howard, Reising file for re-election The filing period for the Nov. 5, 2024, election for Wylie ISD’s Board of Trustees is nearing its Aug. 19 deadline. The board of trustees, comprising seven members elected for overlapping four-year terms, plays a crucial role in...

read more
New theme, new school year

New theme, new school year

Cox Elementary administrative staff, from left, Assistant Principal Angela Clark and Principal Krista Wilson, along with others, represented the Cox Coyotes at the district’s convocation at the Montgomery Center at Wylie High Tuesday, July 30. Courtesy Wylie ISD Wylie...

read more
Tax holiday for school supplies

Tax holiday for school supplies

Items such as a backpack and the supplies shown are tax exempt but a purse or handbag is not. As Texas students prepare to go back to school, their parents can save about $8 for every $100 they pay for clothes or supplies, Texas Comptroller Glenn Hegar said. The...

read more
Subscribe Love